Recreation Deck Update
Posted on Oct 22nd, 2014
On Thursday October 23, 2014 Trinity ERD will be onsite to take two core samples of the recreation deck to analyze and determine what is the cause of the tennis court failure along with the white substance oozing from the tiled area. Expected results in 2 to 3 weeks after these samples are taken.
Garden Area: Please pardon our progress as OWT maintenance staff is decking the garden area. This work will take only a week or so to complete therefore the garden gazebos and some of the perimeter grills will be unavailabe at times. Thank you for your understanding.
Tennis Courts: The AOAO consultant, ADL is working with Kemper, the water proofing company and Mid Pac tennis in determing the cause of the court lifting and further testing is underway, results are expected soon.
Tile: The white substance coming up from the tile is being investigated as well by ADL and WJE to determine the source