400/440 Keawe Construction
Posted on Feb 23rd, 2015
The property directly behind OWT: Auger pile work begins Monday 23,2015. Initially test piles will be installed which should take 2 days. This work will lapse for approximately a week while the engineers check the results. Then will again commence for the production work which will last about 7 weeks. During this period some grading activities will take place, so earth work equipment will be in operations.
Please contact the management office with any questions or concerns.
No Comments